You are here: Home > Client News » ABM Precast Solutions

ABM Precast Solutions

ABM Precast Solutions
ABM Precast Solutions is a global market leader in construction, civil engineering and the manufacturing of precast concrete products. ABM has an unrivalled track record in design and construction projects and complex precast concrete applications.
ABM PRECAST SOLUTIONS LTD
Ollerton Road
Newark
Nottinghamshire
NG22 0PQ
United Kingdom

Follow

1) Disruption to traffic on the canal was minimal. Walls of the Matière bridge were craned into position with only limited need for over canal working

5 image available

Faced with a failing jack-arch bridge over the Birmingham Canal in Smethwick, Sandwell Borough Council and their engineering consultants Jacobs UK Ltd. have opted for a radical solution. A Matière pre-cast concrete arch from ABM Bridge Systems has been installed alongside a century old brick arch structure and an earlier Brindley designed bridge of 1772. The new bridge spans the canal and towpath and is sympathetic in profile and external finish to the earlier structures.

The new bridge completes a programme of works to upgrade bridge decks in the area to meet EU Directive 89/460/EEC for conveying 40 tonne trucks. A council survey in 1994 found the older brick bridges satisfactory, but serious deficiencies in the main beam of the jack-arch extension. These deficiencies were remedied, but a recent resurvey by Jacobs found substantial deterioration and a decision was made to design a replacement for the failed bridge section while retaining the older, but sound, brick arch bridges.

In considering the replacement, the Council considered carefully the practical and aesthetic requirements, including the heritage value of the site. British Waterways, the owner of the original Brindley bridge, were consulted and agreement was reached to use an arch structure in preference to conventional piers and deck. British Waterways also agreed to hand over their heritage bridges to the control of the Council so that future maintenance could be administered by a single body.

British Waterways were insistent on keeping the canal open to navigation during the construction works. This precluded the use of a cast in-situ arch and after consideration the three element pre-cast Matière soil-interactive arch was selected.

ABM is the UK and Ireland licensee for the Matière system, of which there are over 10,000 installations throughout the world. Within the catalogue there are many arch and box bridge configurations, but all have in common the same 4-pin design which provides stability during construction with a single element overbridging unit so that possession time and disruption to under-bridge traffic is minimised.

Main contractors Currall Lewis & Martin (Construction) Ltd. began work in January 2007 on the demolition of the old bridge and the completed structure was handed over in early November. Complications arose because utility services were incorporated in the deck of the old bridge. These were supported by a temporary space frame structure during the works. This gave rise to access difficulties for the placement of the Matière outer arch ring of the bridge that were overcome by the use of a beam and chain support system to allow the ring to be manoeuvred under the service bridge.

The new road bridge is formed from three specially shaped rings with an overall diameter of 9.2 metres. The original canal bridges are flattened arches and so the lower sections of the Matière arches are buried in the earth to give the correct height to span ratio with a navigable height of 4.6 metres.

Disruption to traffic on the canal during the works was minimal. The walls of the Matière bridge were craned into position with only limited need for over canal working. Canal traffic did need to be stopped as the overbridging elements were placed, but once these were fully positioned canal traffic could proceed unhindered as waterproofing, backfilling and compaction proceeded.

The completed structure is faced with class A blue engineering brick, respecting the heritage of the site, but also offering practical advantages of long life and low maintenance. Detailing in the brickwork has been used to emphasise the curvature of the arch and recycled bricks from the old jack arches have been used for towpath paving. The new arch echoes the symmetry of the earlier structures and creates a pleasing sight line.

 

More Information

Mike Sanderson, Business Development Manager, Tel. +44 (0)1777 872233
E-mail: mike.sanderson@abmeurope.com Web: www.abmeurope.com
ABM Precast Solutions, Ollerton Road, Newark, Nottinghamshire, NG22 0PQ

Release issued: December 18, 2007

Email this page


 

Browse Articles
< Previous | Next >

Contact
PR Services
Newsletter Sign Up
© Ainsworth Maguire PR